DRIVERS on the M53 near Cheshire Oaks are facing 10 months roadworks from the end of this week.
A £7 million programme of safety improvements to barriers along a section of the M53 between Ellesmere Port and Stoak begins on Friday (November 24).
National Highways is replacing large sections of ageing steel safety barriers in both the northbound and southbound verges and central reservation between junction 9 and junction 11 of the motorway.
A major feature of the improvements involves replacing some of the steel barriers in the central reservation with a concrete barrier. These provide improved safety for motorway users and require less maintenance – meaning less disruption for drivers.
The ten-month project will start on Friday and is expected to be completed next August. Planning for the work has been done in consideration of shoppers heading to and from the Cheshire Oaks complex with plans to remove traffic management for the forthcoming Christmas and New Year holiday period.
National Highways project manager Ross Hepburn said: “This is an important project to improve safety along this busy section of the M53 by replacing ageing steel barriers with brand new steel barriers and – where favourable ground conditions and foundations allow – sections of concrete safety barrier.
“We’ll be working around the clock but doing all we can to minimise inconvenience to motorway users including working in short sections along the carriageway where possible so drivers aren’t met with miles and miles of traffic management.”
The new barriers will be installed along the northbound and southbound carriageways first before moving into the central reservation. Drainage repairs will also be taking place to make the best use of the traffic management and minimise inconvenience to drivers.
MOST READ
- Flintshire resident celebrates £1,000 win on the People's Postcode Lottery draw
- Take a look around 'magnificent' seven-bedroom home for sale in Wrexham
- Why Caergwrle three-way traffic lights are in place and when they are set to end
Traffic management will include narrowed lanes, a 50mph speed limit and – until mid-December - a lane closure on the link road from the southbound M53 to the eastbound M56 at Stoak Interchange. Overnight lane closures will also be taking place throughout the project.
Some overnight full carriageway closures to install traffic management will be required at various times with the first – between 8pm and 6am – on Friday (24 November) to install the traffic management.
Throughout the work drivers using this section of the M53 are advised to get into the habit of planning journeys - checking for traffic conditions before setting out and using alternative routes should they wish to avoid any congestion.
Live traffic information is always available at www.trafficengland.com. Updates will also be posted to X (Formerly known as Twitter) @HighwaysNWest and Facebook – National Highways: North-West.