NINE weeks of roadworks are starting tomorrow on the A483 in Wrexham.
The major resurfacing works are to replace the road surface that has "reached the end of its serviceable life" between J7 Rossett to the Wales/England border.
The majority of works, which start on Sunday (February 5), will be carried out under contraflow which will allow the A483 to remain open to one lane of traffic in either direction. There will be full overnight closures at certain times to install and dismantle the traffic management system.
February work schedule:
Week 1 (5/2/23 – 11/2/23)
February 5 and 6:
Daytime single lane closures in both directions.
Overnight single lane closure northbound.
Full overnight closure of the southbound carriageway, including Junction 7 southbound slip roads. Local diversion in place.
February 7 onwards:
24-hour contraflow, i.e. one lane in each direction. Junction 7 northbound on and off slips will be closed during this time.
February 9 and 10:
• 24h traffic lights on Junction 7 Rossett Interchange roundabout.
Week 2 (12/02/23 – 18/02/23)
February 12 to 18:
24-hour contraflow.
Week 3 (Sun 19/2/23 – Sat 25/2/23)
February 19 to 25:
24-hour contraflow.
February 23 and 25
Traffic lights on Junction 7 Rossett Interchange roundabout during the daytime.